Pentagon budget 2024: New PSA mindset alters construction and delivery plan for carrier Kennedy

Pentagon budget 2024: New PSA mindset alters construction and delivery plan for carrier Kennedy

Source Node: 2538792

24 March 2023

by Michael Fabey

The US Navy is altering the carrier John F Kennedy’s delivery schedule. (Michael Fabey)

The new US Navy (USN) Post Shakedown Availability (PSA) plan for aircraft carriers is pushing back the expected delivery date for the Ford-class John F Kennedy (CVN 79), but the service anticipates a more operationally capable ship at delivery, and there is no expected changes for vessel deployment or related operations, programme officials told Janes.

“CVN 79 delivery date is being adjusted to July 2025 to support a revised ship delivery/post-delivery strategy,” the USN said in proposed fiscal year (FY) 2024 budget documents released by the navy.

“The navy is implementing a strategy to pull baseline work from the Post Shakedown Availability into the construction period in order to provide more capability at ship delivery,” the USN said. The new date is about a year later than the USN had recently marked as a delivery date.